BUILDING SIZE 250' x 200' = 50,000 sf

TABLA CALCULATION

POST AND BEAMS (FRAMES)
 
TOTAL SQUARE FEET OF DECK WITH CANTILEVER 53,600


AREA TO BE DEDUCTED FROM DECK TOTAL
Count Width Length  
External Columns 28 8ft 6ft   1,344
Internal Columns 35 8ft 8ft   2,240
 
Ramp Wall 2 70ft 16ft   2,240
Exterior Cantilever 1 4ft 900ft   3,600
Interior Cantilever 1 4ft 900ft   3,600
  13,024
 
Balance of Building - Deck40,576
 
LABOR CALCULATIONS (ERECT ONLY)
$ per hr
Cantilever sf/mhr rate
7,200 sf 100
Ramp
2,240 sf 60
Drops
3,584 sf 50
Floor
40,576 sf 300
Button Edge
780 sf 40
 
 
 
LABOR CALCULATIONS (REMOVAL ONLY)
$ per hr    
Cantilever sf/mhr rate
7,200 sf 100
Panels
36,976 sf 600
Drops
3,584 sf 50
Ramp
2,240 sf 60
Reshoring Props
50,000 sf 833
  
 
 
 
TOTAL SQUARE FEET OF DECK WITH CANTILEVER 53,600


AREA TO BE DEDUCTED FROM DECK TOTAL
Count Width Length  
External Columns 28 8ft 6ft   1,344
Internal Columns 35 8ft 8ft   2,240
 
Ramp Wall 2 70ft 16ft   2,240
Exterior Cantilever 1 4ft 900ft   3,600
Interior Cantilever 0 0ft 0ft   0
  9,424
 
Balance of Building - Deck44,176
 
LABOR CALCULATIONS (ERECT ONLY)
$ per hr
Cantilever sf/mhr rate
3,600 sf
Ramp
2,240 sf
Drops
3,584 sf
Floor
44,176 sf
 
   
 
 
 
LABOR CALCULATIONS (REMOVAL ONLY)
$ per hr
Cantilever sf/mhr rate
3,600 sf
Floor
44,176 sf
Drops
3,584 sf
Ramp
2,240 sf
Reshoring Props
50,000 sf
 
 
 
 Total
 LABOR COST PER SQUARE FOOT
 Total
 LABOR COST PER SQUARE FOOT
 
EQUIPMENT
TOTAL AREA 50,000
ADD EXT. CANTILIVER 3,600
 53,600
 
 
PANELS
  53,600$2.00/sq. ft.$107,200.00
 3 Months$321,600.00
RESHORE
  50,000$0.50/sq. ft.$25,000.00
 2 Floors $50,000.00
     
  3.5 Months $175,000.00
   
TOTAL MATERIAL$496,600.00

LABOR
Erect
 12 Floors
Removal
 12 Floors
Button Edge
 12 Floors
Reshore Operation
 12 Floors
   
TOTAL LABOR
   
PROJECT TOTAL
 
 
EQUIPMENT
TOTAL AREA   50,000
ADD EXT. CANTILIVER   3,600
  53,600
 
 
WET DECK EQUIPMENT 2 Floors
107,200 $ /sq. ft.    
  3 Months  
RESHORE 1 Floor
53,600 $ /sq. ft.    
  2.5 Months  
PLYWOOD 2 Floors
3,752 $ /sheet    
         
TOTAL MATERIAL

LABOR
Erect
  12 Floors
Removal (includes reshore operations)
  12 Floors
 
       
 
       
   
TOTAL LABOR
   
PROJECT TOTAL
   
Project Total
Square feet total 600,000 SF / sq Ft.
Project Total
Square feet total600,000 SF /sq. Ft.